Booster compressor station as part of the fuel treatment system for the peak GTPP-100MW at Novopolotsk CHPP

Number of units: 2

Designed for: treatment and feeding fuel gas into turbines

Version: container

Inlet pressure: 1 MPa

Outlet pressure: 3 MPa

Capacity: 19,044…21,960 kg / h (unit)

Commissioning: project was completed with the delivery of gas compressor station to the facility

Customer: Siemens Energy AB (for RUE Vitebskenergo)