Press-center

In composition of the FGTF for the power supply complex of Kharasavey field, an auxiliary boiler room has been prepared for operation

22 September 2021

Start-up and adjustment works of a fuel gas treatment facility (FGTF) ENERGAS for the autonomous power supply complex are being completed at the Kharasavey field of PJSC Gazprom.

FGTF is a multifunctional complex of two modules operating in cascade scheme. Fuel gas treatment module No. 1 (FGTM-1) is intended for preliminary separation, filtration and pressure reduction of the incoming gas. Then the fuel enters to FGTM-2, where the its final purification, flow measurement, heating and additional pressure reduction take place.

Process flow scheme of FGTM-2 includes a packaged boiler room (PBR) with a total useful thermal capacity of 0.6 MW. Integrated PBR prepares intermediate heat carrier for gas heating subassembly and consists of 2 water-heating boilers – working and standby. In addition to the main function, this equipment will provide the own needs of the module No. 2 – the generated heat will be used to heating its premises.



The boiler room is placed in a separate compartment docked with the main enclosure of the FGTM-2. It is equipped with engineering systems and its own fuel supply unit with devices for filtering, pressure reducing and metering of gas. The operation of the boiler room is fully automated, boilers automation and common local control system of PBR are integrated with the ACS of FGTF.

The heat generating equipment is completely ready for pre-start tests and routine operation as part of a multifunctional gas treatment complex.

Previous news Back to the list Next news