Booster compressor station as a part of the gas treatment system for the GTU-CHPP of Yarega field (power supply complex "Yarega")
Number of units: 4
Designed for: treatment and feeding fuel gas into turbines
Version: arctic
Inlet pressure: 0.55…0.9 MPa
Outlet pressure: 4.5…5 MPa
Capacity: 10,770 m3 / h (unit)
Commissioning: November 2016
Customer: LLC "LUKOIL-Energoengineering" (for the LLC "LUKOIL-Komi")
Gas type:
Natural gas