Press-center

The compressor unit No. 2 has been tested as a part of the BCS of fuel gas for the Grozny TPP

23 January 2019

The gas treatment and gas supply system for Grozny TPP is a booster compressor station consisting of three units.

In addition to the gas compressor aggregate No. 1 earlier prepared for operation, the unit No. 2 successfully passed adjustment and its own testing. This allows Grozny power engineers to conduct a full range of tests of the power plant’s second power unit and put it into operation in a timely manner.



In the future, the technical specialists of ENERGAS will perform the start-up works on the booster compressor No. 3. This is an important stage of the pre-launch activities at the TPP.

The basis of the Grozny TPP is two Siemens gas turbine units of type SGT5-2000E with capacity of 180 MW each. The planned electric capacity of the power plant is 360 MW. The main and reserve fuel for turbines is natural gas.

The operating company of the new facility is OGK-2 PJSC. The project is being implemented by the Gazprom EnergoHolding (GEH) Group within the framework of the system of capacity supply agreements (CSA). The Grozny TPP is the final CSA project in the GEH Group.



Previous news Back to the list Next news