The joint Russian-Swiss project in Western Siberia is entering its final phase

27 April 2018

At the BPS-2 site of Konitlor field of the Komsomolskneft oil and gas production department (Surgutneftegas PJSC) there were performed start-up and adjustment works on small gas compressor unit. SGCU is a part of the low-pressure booster compressor station and designed for the pumping of associated gas with inlet pressure close to vacuum (0...0.09 MPa).

The adjustment of SGCU has been completed with own (individual) tests. There is checked the functioning of process, compressor and electrical equipment and automated control system.



Put into operation of the small unit will take place after the comprehensive 72-hours testing.

The project is experimental, its goal is to check the operability of this type of equipment in the climatic conditions of Western Siberia and its compliance with the operational requirements adopted at the facilities of Surgutneftegas.

Design and production of pilot SGCU were performed by the Swiss company Enerproject SA. The step-by-step commissioning of the unit (erection supervision, start-up and adjustment works, and cycle of tests) is being conducted by the leading engineers of the ENERGAS Group which is official representative and partner of the Enerproject SA in Russia.