At the Southern Vatlor there are being mounted low pressure compressor units
9 September 2018
Two booster compressor units (BCU) are designed for pumping associated petroleum gas of the first separation stage coming from the booster pump stations of the following fields of PJSC Surgutneftegas: South-Vatlor, Vatlor, Suryogan, Verkhnekazymskoye, field named after I.N. Logachev.BCUs, created on the basis of screw oil-filled compressors, will continuously implement a final purification, compression and feeding of APG to the external gas pipeline at pressure of 2.2 MPa. The capacity of each BCU is 10,000 m3 / h.
The gas-booster equipment was delivered with a high degree of prefabrication what significantly reduces the duration of the pre-starting stage.
Currently, there are carried out erection works at the site of operation. There are completed installation, alignment and fixing on the foundations, as well as large-block assembly of BCU. The local automated control systems (in separate compartments) and air-cooling units of the compressor units have been mounted. The piping arrangement and electrical power connection are being performed.

Units will be included in the compressor station of low separation stages (CSLS) of South-Vatlor field. All works on the commissioning of this process equipment, including erection supervision, adjustment, individual testing and integrated tests will be performed by specialists of the companies group ENERGAS.
Packaged units in arctic version are designed taking into account the extreme operating conditions (minimum air temperature is minus 55°C, average air temperature of the coldest five-day period is minus 43°C).
BCUs are completely automated; they are equipped with life support systems (heating, ventilation and lighting) and safety systems (fire detection and fire fighting, gas detection, alarm).