ENERGAS compressor unit-simulator has been prepared for operation as a part of the Training Center of OJSC Surgutneftegas
26 March 2016
At the West-Surgut field (Khanty-Mansi Autonomous Area – Yugra), there is created Training Center of OJSC Surgutneftegas – Polytechnic Training Center. The Center is equipped with modern simulators, computer classes and laboratories. Here at the special ground there are installed training analogs of modern equipment operating in the fields of the company.
In training ground there will operate a compressor unit of the company ENERGAS made on the basis of a screw oil-filled compressor. This unit-simulator compresses air (up to 0.6 MPa) for educational demonstration of technological processes at the gathering and pipeline transportation of gas.
Compressor unit (CU) will be used when training of specialists of the appropriate profile. Capacity of CU varies in the range of 0...300 m3 / h and is adjusted by a two-tier regulation system (bypass line and spool regulation).

At CU inlet there is installed air treatment system – high efficiency separator similar to inlet scrubbers for gas filtering which are built-in in compressor units operating at facilities of the Surgutneftegas.
The unit is fully automated. The control system implements preparation for start, start-up, shutdown and maintaining the optimum operating mode of the unit; it controls process parameters; it provides automatic protection and alarm system; it handles the parameters of the workflow and emergency events with the issuance of information on the standard protocol of exchange.
Currently, CU passed 72-hour comprehensive testing as a part of the Training Center. There has been checked the operability of process, compressor and electrical equipment and ACS. In the course of test run, the CU worked out in a routine mode, flawlessly.
The whole set of works on commissioning of the unit-simulator has been performed by the service engineers of the company ENERGAS.