Press-center

The next ENERGAS Group project for the power mechanical engineering enterprises is entering its final phase

28 October 2018

At the site of UEC-UMPO test bench, the engineers of the LLC ServicENERGAS (ENERGAS Group) perform a set of works on commissioning of booster compressor unit. BCU is designed for uninterrupted fuel gas feeding into the testable gas-turbine engines (GTE) of type AL-31ST according to the set parameters on purity, pressure, temperature and flow rate.



BCU, supplied by the company ENERGAS will compress gas to the required operating level (2.8…3.2 MPa) and feed it to the gas generator of drives in the process of their testing.

The equipment was developed on a special project; it is designed for operating under high intensity of starts and shutdowns as well as various duration of testing. Capacity of BCU is 6,500 m3 / h.

Currently, there are completed start-up and adjustment works. In addition to the adjustment, technicians have conducted an own tests of BCU. There was checked the operability of process, compressor and electrical equipment.

In the future, service engineers will carry out individual check of two-tier system of automated control and regulation, comprehensive testing of compressor unit in conjunction with a GTE, as well as training of the operating personnel of the customer.

This project is being implemented within upgrade of bench of the PJSC UEC-Ufa Motor-Building Production Association. Here are equivalent-cyclic tests of gas-turbine drives used in gas pumping units and power plants.