Press-center

At the GTU-TPP site in Elabuga, the own tests of comprehensive gas treatment system took place

30 October 2018

In Elabuga, the specialists of the ServicENERGAS (part of the ENERGAS Group) have completed an adjustment of fuel supply equipment for the GTU-TPP under construction.

The equipment complex comprises a gas treatment unit and a booster compressor station consisting of two units. The main functional is to provide the design parameters of fuel gas on purity, temperature, pressure, and flow rate.



The capacity of the comprehensive gas treatment system is 8,240 m3 / h. All units are automated; local ACS will be integrated into the APCS of the thermal power plant. The version of aggregates – in separate enclosures; block-modules are equipped with safety and life support systems.

In the course of own tests, the service engineers have checked the operability of process, compressor, metering and electrical equipment as well as local ACSs. It is planned integrated testing of gas treatment system during the 72-hour test-run of the entire GTU-TPP.

Previous news Back to the list Next news