The first power unit of the Pregolskaya TPP will be put into operation as early as current year

19 May 2018

In Kaliningrad, the construction of the Pregolskaya TPP continues. The customer of the construction is Kaliningrad Generation LLC. The project is managed by LLC Inter RAO - Electricity Generation Management. The general contractor is Inter RAO - Engineering LLC.



The new power plant will consist of four combined cycle gas turbine units. Each CCGT includes the following equipment:
  • gas turbine of type 6F.03 with capacity of 77.9 MW produced by the Russian Gas Turbines LLC;
  • waste-heat boiler manufactured by the Machine-Building Factory of Podolsk JSC;
  • steam turbine produced by Power Machines PJSC.
The plant is located in the territory adjacent to the existing Kaliningrad CHPP-2. The commissioning of Pregolskaya TPP will make Kaliningrad's power grid more maneuverable.

The builders intend to commission the first power unit as early as current year. The fourth one is scheduled to be commissioned in a year. The total installed capacity of the TPP is 456 MW. This will be the most powerful power plant of the new generating, which will become the basic of the energy security of the entire region.

Fuel for turbines is natural gas. Its design parameters for purity, temperature, pressure and flow will be provided by the comprehensive gas treatment system (GTS) of ENERGAS. GTS includes a booster compressor station of four units, a multipackaged gas treatment unit and a control module.