At the BPS of the South-Vatlor field, the specialists of the ServicENERGAS have started to adjust the gas compressor units

11 October 2018

At the site of the compressor station of low stages of South-Vatlor field (the BPS area), the technical specialists have started to adjust the two booster compressor units. These BCUs are designed for pumping associated petroleum gas of the first separation stage coming from the booster pump stations of the following fields of PJSC Surgutneftegas: South-Vatlor, Vatlor, Suryogan, Verkhnekazymskoye, field named after I.N. Logachev.

The units, created on the basis of screw oil-filled compressors, will continuously implement a final purification, compression and feeding of APG to the external gas pipeline at pressure of 2.2 MPa. The capacity of each BCU is 10,000 m3 / h.

Start-up and adjustment works will be completed with own tests and then with comprehensive check of equipment as a part of the facility.



All the activities on the BCU commissioning are being performed by service engineers of the companies group ENERGAS.

Packaged units in arctic version are designed taking into account the extreme operating conditions (minimum air temperature is minus 55°C, average air temperature of the coldest five-day period is minus 43°C).

BCUs are completely automated; they are equipped with life support systems (heating, ventilation and lighting) and safety systems (fire detection and fire fighting, gas detection, alarm).